Test scope: what end-of-line testing must catch

Wrong wires, missing parts, shorts, insulation faults and poor crimps should be caught before shipment. Define the test items from the customer drawing, wiring table and acceptance requirements; do not copy engineering validation tests straight onto the production line.

Continuity and miswiring: confirm points and circuits first

Measure point by point at the connector pins and confirm continuity resistance, circuit paths and the orientation of diodes and resistors. The test program must distinguish open, short and miswired conditions; a simple continuity check can miss a shifted pin.

Hipot and insulation: state where voltage is applied and how it is judged

For hipot, specify applied voltage, duration, leakage current limit and test points. For insulation, specify test voltage and minimum resistance. Add discharge and reset steps after high-voltage testing to avoid residual voltage.

Test sequence and fixtures: low voltage before high voltage

Normally run continuity and low-voltage checks before insulation and hipot. Fixtures need poka-yoke, location and an emergency stop. Poor probe contact causes false results, so inspect probes and wire order regularly.

Data retention and traceability: results must reach the part

Bind results to a barcode or batch and record program version, date, operator and retest after repair. If the customer needs a data interface, export the agreed fields. See custom wire harness manufacturing.