What the first article must prove

The first article proves that the drawing, materials, tooling and inspection method can be repeated, not merely that one sample can be built. Check the drawing revision, bill of materials and sample status before approval so an old file is not used to judge a new sample.

Dimensions, wire sequence and branches

Measure the wire lengths, strip lengths, branch positions and connector orientation against the drawing. Check wire colours, gauges and sequence, and confirm label content and position. Record the measuring tool and readings; repeat key dimensions and use the average.

Crimping and connectors

Check that strands are visible in the crimp, insulation does not enter the crimp zone and the terminal is not deformed. Record crimp height and pull force as the project requires. Connectors must seat fully, latches must hold, terminals must not back out, and sleeves and seals must all be present.

Electrical and fit verification

Run continuity, short-circuit and insulation checks to the inspection plan, adding a dielectric test where specified. Fit the sample into the target device or an equivalent fixture and confirm bend radius, fixing points and mating space. Correct any interference on the sample before releasing the batch.

Records and sealed sample

After approval, keep the inspection records, test data, drawing revision and key tooling settings, and seal a sample confirmed by both sides. Later batches follow the sealed sample and controlled documents; re-approve the first article whenever material, process or drawing changes.